# Building permit (građevinska dozvola)

Source: https://www.montenegropropertyinvestment.com/glossary/building-permit

**Definition:** A building permit (građevinska dozvola) is the official approval that allows construction of a building to begin. In Montenegro it is issued by the municipality or, depending on the size and type of the project, by the competent ministry.

The rules have changed. Under the 2017 Law on Spatial Planning and Construction of Structures, most buildings were started on a notification of construction (*prijava građenja*) and the documents the law prescribed, filed with the building inspectorate before work began. A building permit was kept for complex structures. A 2025 Law on Construction of Structures gives local governments the power to issue permits for most projects.

So the question is not only whether there is a permit, but which document the building was started on and whether what stands matches it. Work beyond the permit or notification, such as an extra floor, can leave the building, or that part of it, needing [legalisation](https://www.montenegropropertyinvestment.com/glossary/legalisation).

For an [off-plan](https://www.montenegropropertyinvestment.com/glossary/off-plan) purchase, ask for the permit before you pay a deposit, check that it names the developer and the plot, and compare the approved plans with the unit you are buying. When the building is finished, the next document is the [use permit](https://www.montenegropropertyinvestment.com/glossary/use-permit). See [illegal construction and legalisation](https://www.montenegropropertyinvestment.com/guides/illegal-construction-and-legalisation).